×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

When to specify tube to tubesheet joint mock-up test?

When to specify tube to tubesheet joint mock-up test?

When to specify tube to tubesheet joint mock-up test?

(OP)
Are there any guidelines as to when a mock-up of tube to tubesheet joint would be recommended? Such an 'engineering judgement' is highly subjective, similar to defining what is 'critical'.

RE: When to specify tube to tubesheet joint mock-up test?

I would do it any time I was re-tubing an existing HX, or building a new one that isn't exactly like one that the fabricator has made recently.

= = = = = = = = = = = = = = = = = = = =
Plymouth Tube

RE: When to specify tube to tubesheet joint mock-up test?

(OP)
Thank you Ed. In that case, for a new design, it's just an option for the operators? Higher alloy, high pressure, critical service are some of the terms I used to hear for specifying tube joint mock-up. There must be some international standard which recommends to perform Section IX QW 193. Strangely, Section IX QW 193 opening paragraph suggests same.

RE: When to specify tube to tubesheet joint mock-up test?

A tubesheet mock-up should be required regardless if new or re-tubing. The mock-up provides some level of assurance that the tube to tubesheet rolling procedures are sufficient and design. New products don't guarantee any better quality level in comparison to a retrofit. The decision for a mock-up is client driven and some construction codes require it to qualify tube to tubesheet strength welds.

RE: When to specify tube to tubesheet joint mock-up test?

I have had some experience with this.

A Vendor or Fabricator will typically have a tube rolling (expanding) procedure for each of or a number of combinations of tube to tube sheet joint designs. A mock-up and test would be specified for a joint configuration or detail that does not exactly fall within the parameters of the procedure. Say, for example, expanding a work-hardenable material into a close tolerance hole. The Vendor or Fabricator might have a procedure that specifies 8% to 10% tube wall reduction, but that might not apply in this case. Perhaps the optimum joint strength is achieved at 5% tube wall reduction. The mock-up and pull test could be used to find this out.

You also might want such a mock-up and test if the bundle experiences significant temperature differential between tube sheets or between passes in multiple pass exchangers.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources