INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Crushed stone turnaround area

Crushed stone turnaround area

Crushed stone turnaround area

(OP)
I have the need to desing a crushed stone turnaround area for trucks. The soil is about average (2000 psf). The loading value for the trucks should be H20 loading. What would be a good thickness for the stone and what underlayment material should I use.

RE: Crushed stone turnaround area

The stability of the soil below your layer of crushed stone will need to be solid. I would recommend performing a proof roll of the subgrade prior to placing the stone. Make sure any fill placed to build the turnaround is properly compacted. I would also try to keep the stone thickness pretty beefy (10" - 12") if going to be used as a turnaround area by trucks, as the turning movements of the trucks could likely cause rutting in the stone. A layer of woven geotextile below the stone is an option for you also to keep the aggregate separated from the subbase and help distribute loading.

RE: Crushed stone turnaround area

well graded aggregate base will be much more stable and would not require any underlayment unless you have a high water table or soft clay underneath.

RE: Crushed stone turnaround area

Sounds like you're on a budget with this one. Whatever you do, be sure to use CSTC on your upper layer and compact the HE!! out of it. (specify modified proctor and above 95% : 100% is possible!).

RE: Crushed stone turnaround area

Why not do a pavement design using the AASHTO method to calculate the required gravel thickness? You will need the CBR value, the ESALS (you can calculate knowing the number of trucks per day), as well as some other factors. Also make sure the owner knows that the gravel pavement will require periodic maintenance, regrading, etc. Especially since it is a turn-around area where some shoving of the gravel is likely.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources