INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

cast in situ concrete piles

cast in situ concrete piles

cast in situ concrete piles

(OP)
what is minimum time required to pour adjacent cast in in situ concrete piles with center to center distance of 3.2m.we are using reverse rotary method for boring of pile bores.

RE: cast in situ concrete piles

It likely depends on the soil type; in these environs it's not uncommon to have drilled piles @ 3x diameter drilled and concrete cast slightly later...

Dik

RE: cast in situ concrete piles

(OP)
the subsurface strata is sandy from medium to dense.

RE: cast in situ concrete piles

If the holes are excavated immediately prior to concrete placement then a minimum strength of 80% of F'c is recommended before disturbing the adjacent soil. Using high early mix designs, this can be less than 24 hours.

RE: cast in situ concrete piles

sandy soil... any problems with sloughing of the sand? What is the reverse rotary method?

Dik

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources