Question on the required 22.5 Kip (for moment) point load for HS25...
Does impact loading have to be added to this per AASHTO? I don't have a current copy and can find no reference to this. If so, I would expect 30%.
Designing steel grate for a vault lid and it comes into play here.
Does impact loading have to be added to this per AASHTO? I don't have a current copy and can find no reference to this. If so, I would expect 30%.
Designing steel grate for a vault lid and it comes into play here.
Mike McCann
MMC Engineering
http://mmcengineering.tripod.com






RE: HS25 Impact Loading
RE: HS25 Impact Loading
Mike McCann
MMC Engineering
http://mmcengineering.tripod.com
RE: HS25 Impact Loading
RE: HS25 Impact Loading
RE: HS25 Impact Loading
RE: HS25 Impact Loading
RE: HS25 Impact Loading
It's one of those situations where the supplier says that he has done it this way for years with no problems, if you know what I mean. The documented references will help immensely.