Snubber procurement
Snubber procurement
(OP)
During snubber procurement as a stress analyst what are the parameters to be provided to a vendor.
Say the snubber linear direction is in x direction.
Then I should provide the occasional load in x direction for which the snubber has to be designed and the thermal displacement in x direction.
Or should I also provide Displacements in y and z direction also.
The displacements mentioned above are displacements of the point where the snubber get connected to piping.
Say the snubber linear direction is in x direction.
Then I should provide the occasional load in x direction for which the snubber has to be designed and the thermal displacement in x direction.
Or should I also provide Displacements in y and z direction also.
The displacements mentioned above are displacements of the point where the snubber get connected to piping.
Thanks and Regards
Parijat Bandyopadhyay





RE: Snubber procurement
During snubber purchase what are the parameters to be provided to a vendor?
Say the snubber linear direction is in x direction. X is the stroke direction.
Then a purchaser should provide the occasional load in x direction for which the snubber has to be designed and the thermal displacement in x direction.
Or should he also provide displacements in y and z direction also i.e. for stroke calculation only x displacement is needed or y and z are also needed?
The displacements mentioned above are displacements of the point where the snubber get connected to piping.
One more thing : The stroke is considered from the middle of the snubber or from end to end of the snubber?
Thanks and Regards
Parijat Bandyopadhyay