INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

ASME Sec 1 Piping.

ASME Sec 1 Piping.

ASME Sec 1 Piping.

(OP)
The company I work for have been awarded a contract to install ASME Sec 1 Piping (Pre-fabricated spools supplied by others)on a new boiler. project is in Northern Canada. My company are the holders of an ASME "S" Stamp. As far as the data reports are concerned in my mind our obligation to satisfy the code is to sign the certificate of field assembly on the back of the Fabricators P4A form. We have been requested to supply name plate for the piping install I have no issue with this. My question is do we have to generate our own P4A form for the install & is there any issue with my company supplying the name plate. Thanks George.

RE: ASME Sec 1 Piping.

Quote:

My question is do we have to generate our own P4A form for the install & is there any issue with my company supplying the name plate.

No, see PG-109.1 and PG-109.2 of Section I.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.