INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

TENSION ANCHROGE OF BEEM REINFORCMENT IN COLUMNS(thin Section)

TENSION ANCHROGE OF BEEM REINFORCMENT IN COLUMNS(thin Section)

TENSION ANCHROGE OF BEEM REINFORCMENT IN COLUMNS(thin Section)

(OP)
How to deal with the tension reinforcement anchorage in columns(10" depth) with 90deg hook.
Ldh REQ from int. face of column is 16.43in for #6 bar where as we have on 8" depth available after deduction of clear cover 2".

RE: TENSION ANCHROGE OF BEEM REINFORCMENT IN COLUMNS(thin Section)

Perhaps a freehand sketch would help in understanding your question.

BA

RE: TENSION ANCHROGE OF BEEM REINFORCMENT IN COLUMNS(thin Section)

In any case, two usual solutions are used:

1. Diminish the diameter of component rebar, to make the splice or anchorage length smaller.

2. Leave preinstalled the appropriate rebar in the column in the 90 deg shape, then have the splice with the beam, so you can have any length of splice in both the column and the beam.

In some cases the extant depth of column is anyway inadequate because there's not enough concrete to take the forces imparted by the rebar. This can be revealed by a strut and tie scheme. This I remember has been treated in this forum, at least in the context of minimum depth of footings for cantilever walls.

RE: TENSION ANCHROGE OF BEEM REINFORCMENT IN COLUMNS(thin Section)

(OP)
Dear ishvaaag :
Can you please further clarify option # 2 .it is more appealing , how to install 90deg pre-install re bar then splice with the beam

RE: TENSION ANCHROGE OF BEEM REINFORCMENT IN COLUMNS(thin Section)

Likely need more smaller diameter bars. If this doesn't work may need a larger column.

RE: TENSION ANCHROGE OF BEEM REINFORCMENT IN COLUMNS(thin Section)

What reinforcement at this location is tension reinforcement? If the column is only 10" deep, it can't be taking much moment from the beam.

RE: TENSION ANCHROGE OF BEEM REINFORCMENT IN COLUMNS(thin Section)

(OP)
Column Size is 10"x42", it will behave as shear wall, its my thinking whts ur suggession, further connection detail is already attached for reference.

RE: TENSION ANCHROGE OF BEEM REINFORCMENT IN COLUMNS(thin Section)

I attach the sketch of the detail I refer to. By including the 90 deg supplementary rebar one gets proper anchor to the column. Other thing is that the tensile force is anyway limited to some value, since high forces may become too much for small depth anchoring elements, in this case, the column.

RE: TENSION ANCHROGE OF BEEM REINFORCMENT IN COLUMNS(thin Section)

I don't see where it would make any difference if you use a U shaped bar or a bar that extends from the column into the beam. In the end you are looking at the developement length of a hook and if you can't develop the needed reinforcement something will have to change.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources