INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Steel Base PL weld - D1.8 AISC 341

Steel Base PL weld - D1.8 AISC 341

Steel Base PL weld - D1.8 AISC 341

(OP)
For an eccentrically braced frame (EBF), AISC 341-10 seems to discourage partial pen welds via the 200% capacity requirement (section D2.5b(1)).
For base plate welding - W12x136 column to 2.5" thick plate - seems like the fabrication must include weld access holes, with CJP welds at flanges - just like a special moment frame beam to column, given the next uplift axial load is more than about 500 kips.
However, I have seen many base plates at seismic frames designed by others - SCBF and SMF - that do not have weld access holes at the column to base plate.
Seems like if CJP are required (due to demand), weld access holes are required. Don't know how to get a CJP without using them. Agree?

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources