INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Single Pipe Piling Question

Single Pipe Piling Question

Single Pipe Piling Question

(OP)
I am working on calculating the maximum allowable lateral working load that may be applied to a marine bollard that is sitting on top of a foundation that has a single pipe piling set 25ft deep. I have used Broms Method and the CLM2.0 spreadsheet to arrive at similar values. However, the bollard sits at the top of a tall river embankment. Thus, the riprap slope drops off in front of the bollard towards the river. The lateral force would come from vessel mooring lines and would therefore be pulling in the direction of the dropoff. My question is this: how far back must the bollard sit from the edge of the embankment for the maximum allowable loads I have calculated to be valid?

Thanks,
Will

RE: Single Pipe Piling Question

I would say the passive pressure must exit before the dropoff or you must reduce the passive pressure that acts.

RE: Single Pipe Piling Question

(OP)
BigH,

Thanks for the response. It is helpful.

Looking at this problem from another perspective. Suppose we drove the piling at the top of the riprap slope with little or no offset back from the edge. This would then essentially reduce to a problem of a single piling under lateral load driven into a slope. I would then need to find the minimum embedment to achieve a particular lateral working load. However, all the material I have found so far applies only to level ground. Can you (or anyone else) point me to a method (analytical or numerical, i.e. computer program or spreadsheet) that would allow me to solve this problem of a single pile under lateral load driven into sloped ground.

Thanks, Will

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.