Roof removal analysis
Roof removal analysis
(OP)
Hello folks,
I interested in removing the roof of a building as this is the only way to put new equipment. Because of this I need to analyze the problem and see whether the building is stable while the roof is removed. In parts of the building I must take out roofing panels, and perhaps in another part of the building, one or two braces. Could someone please guide me as to what things you would consider.
Of course I must consider wind loads, but I am not sure how to use the National Building Code of Canada for a structure with no roof.
Any help would be greatly appreciated. Thank you very much.
I interested in removing the roof of a building as this is the only way to put new equipment. Because of this I need to analyze the problem and see whether the building is stable while the roof is removed. In parts of the building I must take out roofing panels, and perhaps in another part of the building, one or two braces. Could someone please guide me as to what things you would consider.
Of course I must consider wind loads, but I am not sure how to use the National Building Code of Canada for a structure with no roof.
Any help would be greatly appreciated. Thank you very much.






RE: Roof removal analysis
From 1,000 miles (1609 km) away - can't be much help.
Sketches, dimensions, pic always help...
RE: Roof removal analysis
RE: Roof removal analysis
RE: Roof removal analysis
In this part of the world seismic risk is low.
RE: Roof removal analysis
If so, I think you are safe to take apart the parts of the roof necessary to lift in the equipment, then put it back together. Limit the time when the roof is open, do it in good weather conditions, and you should be fine.
RE: Roof removal analysis