Soldier Pile Embedment Depth
Soldier Pile Embedment Depth
(OP)
Does anybody the procedure to calculate embedment depth for soldier pile with tieback anchors in rock? I looked at Cir. No. 4 but I couldn't get any useful information.
Thanks for your suggestions.
Thanks for your suggestions.





RE: Soldier Pile Embedment Depth
Get yourself a copy of "Foundation Engineering" by Jumikis, 1986 and look at his "Equivalent Beam Method". This will give you procedure for embedment and anchor forces, etc. The FHWA publications on tieback designs are very conservative.
RE: Soldier Pile Embedment Depth
Thank you. I will try to find the book.
Thanks
RE: Soldier Pile Embedment Depth
www.PeirceEngineering.com
RE: Soldier Pile Embedment Depth
Thank you for your sugesstion. Actually, I tried with this procedure. For some reason, I was thinking that I was using a wrong method Tieback anchor wall. Anyhow, thanks a lot for giving a valuable suggestions.
thanks