Smart questions
Smart answers
Smart people
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Member Login

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips now!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

Join Eng-Tips
*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

LINK TO THIS FORUM!

Add Stickiness To Your Site By Linking To This Professionally Managed Technical Forum.
Just copy and paste the
code below into your site.

Partner With Us!

"Best Of Breed" Forums Add Stickiness To Your Site
Partner Button
(Download This Button Today!)

Feedback

"...I think the site is just incredible....I am learning more here than anywhere else before and am looking forward to being able to help someone .... this is my idea of what the Internet is supposed to do..."

Geography

Where in the world do Eng-Tips members come from?
holdpt (Structural)
7 May 12 16:08
Does anyone have any data regarding the relationship between man hours and inspectors?
It would be very helpful for our expected "ramp up" to know how many more inspectors may be necessary.
btrueblood (Mechanical)
7 May 12 17:09
I'd think that would be highly dependent on the product.
PAN (Mechanical)
7 May 12 23:45
holdpt,

This depends on qualification level and experiences of inspector. What's your specific requirement?
stanweld (Materials)
8 May 12 8:36
In a construction project, it also depends on the Customer's contract requirements. There are estimating standards used but they vary from company to company. Take a stab at 3% to 5%.  

holdpt (Structural)
8 May 12 9:10
Allow me to expand on the circumstances.  We are fabricating panels and some modular work for baghouses and SCR's.  We also fabricate large ductwork, both square and round.
The dimensional and welding inspectors are home grown but are quite good.
My concern is going from 4000 mh/wk to 7000 mh/wk.

Thanks.
Helpful Member!  KENAT (Mechanical)
8 May 12 10:07
Simplistically, if you're happy with your current inspection ratio, why not just increase by amount required to maintain that ratio?

Posting guidelines FAQ731-376: Eng-Tips.com Forum Policies http://eng-tips.com/market.cfm? (probably not aimed specifically at you)
What is Engineering anyway: FAQ1088-1484: In layman terms, what is "engineering"?

holdpt (Structural)
8 May 12 11:20
I had been thinking about maintaining the ratio.  It happens to be 4.6%.  Based on stanweld's input and the intensity of my guys' efforts, I feel pretty good about keeping with that.

Thanks all.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!

Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close