×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

concrete formwork question

concrete formwork question

concrete formwork question

(OP)
I have a situtation where perimeter masonry walls support an outdoor patio.  The owner wants to use a structural reinforced slab instead of slab on grade.  I know there are ways around having to shore the slab (light gauge framing supporting slab, composite deck, steel joists, etc.), so this is just a general question.  Have you ever been in this type situation where the formwork was required but would be enclosed by the new concrete structure and have to be... abandoned for lack of a better word?  Thanks.

RE: concrete formwork question

Typically use a 6" void form... this can be a cardboard type or my preference, a foamed plastic type.  This is placed on moderately compacted granular fill (depending on the soils, sometimes no compaction) and the concrete is cast over it.  You can still place a PEVB between the void form and the concrete slab.

Dik

RE: concrete formwork question

We've used the cardboard forms, foam, and metal form deck.  All left in place.  I'd be wary of leaving wood formwork abandoned near a house if you are in termite country.

 

RE: concrete formwork question

@bigengineer: We have done what we call structural slabs on grade for interior applications where for design purposes the slab is considered as a suspended structural slab. This is possible where the underlying soil/base is capable of supporting the weight of the structural slab and construction loads during the construction phase.  
Your post does not mention about your region. If you are in a region where there are no frost protection requirements, then it is possible to place the slab directly on soil/base without using any sacrificial forms or frost protection measures.
  

RE: concrete formwork question

(OP)
Thanks for the replies.  Actually, this is an elevated patio, about 5-6' above grade with perimeter masonry walls.  The owner doesn't want to use fill inside the masonry walls and wants a free spanning r.c. slab spanning between the walls.  There are no access doors, etc to remove form work later.  And again, owner is requesting no fill material.  

I can use a composite steel deck to achieve the spans he wants, but would be cheaper to do some metal decking (non-composite) as form work that is shored a couple/few times between permanent supports.  Like JAE said, this would cause concerns with termites though with abandoned forms.  Maybe form work from treated lumber?

RE: concrete formwork question

You can support metal deck on wood knee walls to cast the concrete and remove the temporary framing after the concrete is sufficiently hard.  Metal deck forming can be less costly than plywood... and you may be able to obtain roof deck (not composite) from a local salvage supplier.

Dik

RE: concrete formwork question

Don't use composite metal decking.  The decking would serve as the structural reinforcement but because it is an exterior deck, it will rust and eventually you would have a slab with no reinforcement.

Use form deck and reinforce with rebar or do one of the other ideas above.


 

RE: concrete formwork question

Agree with JAE.  Use whatever deck will carry the load during construction, but reinforced the slab as if the deck did not exist.

RE: concrete formwork question

Thanks, guys... I should have been a little more emphatic...

Dik

RE: concrete formwork question

I have seen metal decking used as lost formwork on a footbridge project. The slab was reinforced with conventional reinforcement and the metal decking was lest to rust away over time.

Becareful with cardboard void formers. I used them once and they collapsed when the concrete was placed. Very costly.

RE: concrete formwork question

bigenginnerz:
You should have some openings for ventilation... Can have a louvred opening, or simply a steel grate/wire opening to keep birds and rodents out...

asixth:
Cardboard ones work OK, as long as they're kept dry prior to placing and contractors often wrap them in poly and provide a 1/8" or 1/4" masonite board on top to keep the rebar chairs from poking through.

Dik

RE: concrete formwork question


bigenginner - I definitely agree with JAE & Hokie, do not depend on the metal deck for any composite action.  Dik makes a good point about providing a couple of screened openings to ventilate the enclosed void.  You don't mention the plan dimensions, but you may be able to lighten up the deck gauge by fabricating a simple truss from angle stock to hang off the walls and provide additional support at the middle of the deck span.
 

Ralph
Structures Consulting
Northeast USA

RE: concrete formwork question

You could also build another central wall support or piers to cut down on the slab span.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources