INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Concrete sleepers steam curing

Concrete sleepers steam curing

Concrete sleepers steam curing

(OP)
Is anyone aware of the typical duration of the steam curing cycle for concrete railway sleepers? The european standard in force prescribes the temperature gradient and the max temperature of the cycle, but no mention about its duration.

Thanks  

RE: Concrete sleepers steam curing

Call the people that make them. Ask for the ASTM for the sleeper.

Richard A. Cornelius, P.E.
WWW.amlinereast.com

RE: Concrete sleepers steam curing

ASTM would only be concerned with the age at testing and not the concrete production process. ASTM is concerned with materials, product standards and testing procedures.

If this is for a plant production, I would go to the manufacturer (most are European companies) of the equipment used to get some idea of the curing duration time. They know more about the manufacture of the products and relationships between the materials, the plant thermal characteristics (mass is important) and cycling times.

The European standards probably do not prescribe a curing duration because of the wide range of possibilities. The temperature gradient may be very slow, but 6 hours to 24 hours might be common depending on the materials and process. In a controlled plant environment, 8000 psi for a concrete block in less than 12 hours is possible and after that, the hydration and shrinkage is completed. Atmospheric curing will be somewhat slower and depending on the properties desired varied.

Specifying the limit of the maximum temperature does limit the processing cycles to certain methods.

Dick

Engineer and international traveler interested in construction techniques, problems and proper design.

RE: Concrete sleepers steam curing

For ione:

If You are not on the pressure with answer to Your question, please wait 2 weeks. In the midlle of May I'm going to precast factory in Europe where railway sleepers are produced... I will ask.

RE: Concrete sleepers steam curing

ione....curing is done until the appropriate properties are achieved, usually some percentage of the ultimate strength of the material.  This is empirical, depending on the equipment, materials and processes employed.

RE: Concrete sleepers steam curing

(OP)
Thanks everybody for your replies.

KateP should you get useful info during your journey, please consider they'll be welcome.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources