INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Crane Rail Expansin Joints
3

Crane Rail Expansin Joints

Crane Rail Expansin Joints

(OP)
I am looking for specifictions and requirements for crane rail expansion joints.  I work in an industrial complex and we have many large buildings with overhead cranes without expansion joints, I want to get up to speed on the requirements for when we construct a new building.  
 

RE: Crane Rail Expansin Joints

look at AISC Design Guide 7
and
AIST Technical Report 13

RE: Crane Rail Expansin Joints

2
I'm sorry...I have read your post again and realized you are specifically talking about the rail itself.

In short, do not put expansion joints in the rail. Although many have tried to do this with some success, there simply is no good system for it. The rails will wind up cracking at the joints and you will cause undue wear on the crane wheels. The common practice now is to thermite weld the rail joints and allow the rail to grow longitudinally towards the crane stops. The space required for the rail to grow can be a difficult thing to calculate since, along with the crane rail itself expanding, the building does as well.

I believe the subjectt is covered in the attached paper...by one of the foremost industrial building designers.

 

RE: Crane Rail Expansin Joints

Same as Toad.
Even before thermite joints, I was taught to use splices with no allowance.

Michael.
Timing has a lot to do with the outcome of a rain dance.

RE: Crane Rail Expansin Joints

Pad- you're right. Mechanical splices can work well and last for years. The splices are set up to mechanically draw the two ends of the rail very tightly together. Aside from the obvious splice bars, it can be hard to see the splice in the rail itself when done properly.  

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources