INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Sulfur Blocks Melting Plant

Sulfur Blocks Melting Plant

Sulfur Blocks Melting Plant

(OP)
Currently we have sulfur blocks stacked on plant site. We are planning to built a permanent sulfur melting plant. The sulfur came from Claus process and approximately contained 10 ppm H2S before the block was formed. The plant capacity is about 1000T/d. the melted sulfur will be trucked out for sale. Steam will be used for melting. A small boiler may be required to produce the steam required.

Anyone knows proper technology or facility available for this purpose? What are the main challenges for this kind facility?

Thanks,

Yuze

RE: Sulfur Blocks Melting Plant

We did this at a plant I worked at years ago. Dont remember much except that good filtration of the melted suplhur was critical. You would be surprised what was picked up in the blocks as they were originaly laid down.

RE: Sulfur Blocks Melting Plant

I used to use an Ellithorpe remelter that was essentially a vertical truck bed of steam coils that pressed against the coil.

The resulting liquid sulphur flowed down into a series of troughs and then into a heated sump for pumping and storage.  I was forever getting sulphur burns from spattering sulphur, the stench was horrific, and small sulphur fires were not uncommon.  I was quite happy when that job ended.

Suggest you talk with one of the big sulphur movement companies...

RE: Sulfur Blocks Melting Plant

(OP)
Thanks for your replies. We have considered using the steam coil pressed against the sulphur blocks. However, there are a few disadvantage for this option.
1, our sulphur block is about 100 feet. Using the steam coil pressing against it needs to be step by step.
2, In the winter, the weather is very cold the heat loss for the steam coil may be quite significant and the productivity may be low.
3, Since this is a permanent facility and the design life span is for 25 years, the reliability for the steam coil may not meet the life span requirement.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources