INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Intermediate Precast Structural Walls

Intermediate Precast Structural Walls

Intermediate Precast Structural Walls

(OP)
I'm working on an existing building and trying to justify that the tilt-up walls can be classified as "Intermediate Precast Structural Walls".  It looks like the main difference between "ordinary" and "intermediate" is Section 21.4 in ACI318-08.  My problem is that I don't understand exactly that section wants me to do.  My detail to tie the panels together consists of a steel plate that uses post-installed epoxy-grouted threaded rods into each panel.  Based on Section 21.4 I have to determine whether or not my connection is yielding and then develop 1.5*Sy if it isn't.  All of that seems to refer to rebar that is cast into the panel, but I used Appendix D to size my connection.  Is Appendix D sufficient or do I still need to develop 1.5*Sy?  Any ideas out there?

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources