INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Piping componnents modifications

Piping componnents modifications

Piping componnents modifications

(OP)
Hello

If i have an existing  ss piping system  ( size 1" , 1 1/2 " ) which is handling 20 bar pressure and has flanges  valves and filters rated  for #150 which will be changed to new service of 35 bar after installing an upgraded pump , will the flanges valves piping  and filters need to be changed ? please let me know what rating of all these components i will have to change . Also please let me know this is as per which standard
Thanks

RE: Piping componnents modifications

You didn't say what material, however the limit for 150# flanges and fittings is around 20 barg or less. You will almost certainly have to replace all flanges etc with 300# rated components. Check your pipe walls too.

RE: Piping componnents modifications

(OP)
Thanks  C2it for your reply
I will be using SS 316 Material . The pipe line has ball valves , check valves , filter assembly , flanges and rest of the line is welded . Please confirm that i will have to replace only flanges and why only flanges ? Can you please tell me which standard will give these pressure limits for 150 # , 300# etc  for flanges , ball valve , check valve and pipe . What are the various  ratings of the pipes . In which standard I can see this.
Thnaks a lot for your help  

RE: Piping componnents modifications

He said, "check your pipe walls too.", but he meant, "You ... should check everything else as well."

Only put off until tomorrow what you are willing to die having left undone. - Pablo Picasso

RE: Piping componnents modifications

B31.3 I assume or an equivilant piping code. You will need to re-engineer all components for the new pressure rating.

RE: Piping componnents modifications

rocket....

Maximum operating temperature is also important. What is the new max operating temperature ?

At 35 bar, you are essentially installing a new "class"  of piping in place of the old.

-MJC

   

RE: Piping componnents modifications

My guess is that eventually you WILL be replacing everything - as they slowly blow up one by one!!!

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources