arrangement and measurement nx6
arrangement and measurement nx6
(OP)
I have a problem with nx6. Switching the assembly arrangement from on state to an other an assotiative distance measurement doesn't update.
It updates only when I clicked the measurement or update for external change. I have he latest Nx6 version nx605mp10. What went wrong, a part specific setting? I have an old assy works fine new created files fail with an assotiatve measurement.
regards
It updates only when I clicked the measurement or update for external change. I have he latest Nx6 version nx605mp10. What went wrong, a part specific setting? I have an old assy works fine new created files fail with an assotiatve measurement.
regards





RE: arrangement and measurement nx6
Make sure that your components are not just "partially loaded" (in "Assembly Load Options").
Also make sure "Load interpart data" is toggled on (also in "Assembly Load Options").
RE: arrangement and measurement nx6
RE: arrangement and measurement nx6
- loadoptions are ok, partial loading -> unchecked
load interpartdata is checked - all levels,
any other idea?
RE: arrangement and measurement nx6
John R. Baker, P.E.
Product 'Evangelist'
Product Engineering Software
Siemens PLM Software Inc.
Industry Sector
Cypress, CA
http://www.siemens.com/plm
UG/NX Museum: http://www.plmworld.org/p/cm/ld/fid=209