INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Sprinkler tank

Sprinkler tank

Sprinkler tank

(OP)
I'm doing a design acc. to FM, tank capacity 565m3.
Could any one help me with max time for filling the tank?
It'll be filled by potable water from public main.
Thanks in advance.

RE: Sprinkler tank

Per NFPA 22, Section 14.4.2, the design of the fill inlet must be capable of filling the tank within 8 hours.

RE: Sprinkler tank

Does this mean the tank simply has to have an intake sized to allow filling in 8 hours or the pipe to the city main must be large enough to fill the tank in 8 hours? Would it be allowed to have the FD could hook a pumper truck to a hydrant and fill the tank? Or maybe the owner fill the tank with a water truck etc?

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources