INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Cement Storage Facility

Cement Storage Facility

Cement Storage Facility

(OP)
What is the proper value(equivalent fluid density) of portland cement with regards to lateral pressure on a vertical wall that retains dry cement powder?

Also, is it correct to assume 1 sack(94 lbs) of cement(dry) is equivalent to 1 cu. ft. of volume?

Suggestions appreciated.

Thanks!

RE: Cement Storage Facility

I wouldn't just assume the sack of cement is a ft3...but the density of dry portland cement is around 1500 kg/m3 (94 lbs/ft3), so your assumption is correct. I'm not sure what the equivalent fluid density would be...a little bit of google may help.

RE: Cement Storage Facility

Another item to consider; is the 94 pcf the compacted or the bulk density?  For structures that I design the structural density will be for a compacted material that is generally greater than the bulk weight.  I have not designed any cement handling structures but the compacted structural density can be anywhere betweeen 20% to 50% of the bulk density.

RE: Cement Storage Facility

Ref: Design of walls, bins, and grain elevators by Milo Smith Ketchum - Angle of repose = 37.5 degrees, ratio of lateral pressure to vertical pressure = 0.32.
As ad aside: The pressures on the walls of the containers storing granular materials vary considerably during filling and emptying operations. If required, you may refer to ACI 313 for design of silos for stacking granular materials.

RE: Cement Storage Facility

This can vary- The supplier will know the exact number for their product.

I have seen it vary from 90 pcf to 110 pcf  

RE: Cement Storage Facility

Just make sure it can't get wet!!!

RE: Cement Storage Facility

You will also get vertical shear forces that need to be included in the design, unlike liquid loading.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources