INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

NDT on Temporary Hydrotest weld

NDT on Temporary Hydrotest weld

NDT on Temporary Hydrotest weld

(OP)
Good evening sorry my english please.

I'am work in a project on shore and i have a problem with the field quality manager and NDT Manager.
We have performer hydrotest on 32 pipepline by 31.3 code.
In a battery limits we expected a welded(<) plate in a stub pipe (BW) welded on process pipe.

FQM & NDTM want execute a RT Test on whole BW but is a problem's with my progress and program.

I succeeded persuade their of execute a VT(preparation) before weld and VT after first sweep for pipe with Pressur Test <50 Bar and RT on pipe with Pressure  Test >50 Bar.
but my leader don't is pleased.

Please help me..Know you a para. of all codes where to be written exs.

"NDT Type on temporary weld (unlist components or element of process pipe) for pressure Test are company's discretion" or similar?

Thank you!!

P.S.
how to be my English?
please, correct it.





            

RE: NDT on Temporary Hydrotest weld

Please review B31.3, Section 345.9.1 Examination of Welds - see below. I believe (a) applies in your situation.

345.9.1 Examination of Welds. Welds, including
those used in the manufacture of welded pipe and fittings,
which have not been subjected to hydrostatic or
pneumatic leak tests in accordance with this Code, shall
be examined as follows:
(a) Circumferential, longitudinal, and spiral groove
welds shall be 100% radiographed in accordance with
para. 344.5 or 100% ultrasonically examined in accordance
with para. 344.6.
(b) All welds, including structural attachment welds,
not covered in (a) above, shall be examined using the
liquid penetrant method (para. 344.4) or, for magnetic
materials, the magnetic particle method (para. 344.3).
 

RE: NDT on Temporary Hydrotest weld

Had this many of times, unfortunately it is my client who instructs the 100%.

I'm not sure if Section 345.9.1 is applicable as it requires 345.1(c) to be applicable which is that a hydrotest cannot be practically performed.  In this case, it is about the weld of a hydrotest head, so it will hydrotested.

I would think the following clause may apply: 341.4.1(b)(1) not less than 5% of circ. butt to be examined by RT or UT. (v2008/2010)

In any event, you have to perform your risk assessment, not just based on schedule.  Since the joint will be pressurized and your inspectors will be visually examining all joints, I don't think it would be to much to ask to perform 100% UT on the joint.

 

RE: NDT on Temporary Hydrotest weld

A VT will not find problems that will cause catastrophic failure.  

You've got to "look" at the weld internals: RT or UT can do that.  Mag particle will get some sub-surface flaws, but not deep ones.   

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources