INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Car park deck loads
2

Car park deck loads

Car park deck loads

(OP)
Hi, Geotechnical engineer looking at FNDs for single deck of car park, what sort of column loads could be expected for say 9m spans?  The client is adding a raised car park deck to provide additional parking, so it's only one deck that will be supported.  

Also, what sort of differential settlements are acceptable?

Thanks

RE: Car park deck loads

All the loads that will act on the structure. Use load combinations as per code and make a structural analysis to determine how much load will be carried by your columns. There are lots of loads to consider so please consult a structural engineer.

RE: Car park deck loads

(OP)
Thanks, I was hoping someone has experience in designing these things and could give me a ball park figure.  KPa for the deck area would be fine, I could turn that into column loads based on the span...

I'm a  geotechnical engineer not a structural engineer!

RE: Car park deck loads

It depends on the code you are using. Most specially you have to consider the effects of moving loads.

RE: Car park deck loads

(OP)
Eurocodes...

RE: Car park deck loads

Live Load is 2.4 kPa (Car Traffic Only)

For Dead Load you need the slab thickness and topping.

RE: Car park deck loads

Don't forget snow, drifts, wind/seismic, etc, and the possibility of unexpected traffic loads (ie fire trucks)
 

RE: Car park deck loads

Typically in US the load is 50 psf plus dead plus snow/live plus wind, etc AND a 2,000 lb point load anywhere.

CHECK YOUR CODES!!!

RE: Car park deck loads

(OP)
Thanks for your help.  I'm not actually trying to calculate the exact design loads, just trying to get an idea, 1kPa, 5kPa, 10kPa, etc.  What I'm trying to second guess is whether the columns can be supported on pads, or will they need piling.  Being a geotech, I have no real idea how much a car park weighs, but I do know what the ground will take.

RE: Car park deck loads

What is your bearing capacity and soil modulus?

RE: Car park deck loads

C4.8.3
"...vehicles, however, a design load of 40 psf is recommended
with no allowance for reduction according to bay area."

ASCE 7-05

RE: Car park deck loads

Light vehicles (≤ 25 kN gross vehicle weight) = 2kN/m2 or 15kN

Medium vehicles (> 25 kN, ≤ 160 kN gross vehicle weight) = 5 kN/m2 or 90kN

 

RE: Car park deck loads

ItsOnlyMud,
Just use 10kPa as a total of DL + LL.  That gives an ample allowance for what you don't know, which is how heavy the structure will be.  Probably less, but that is a good enough ball park figure for what you need at this stage.

RE: Car park deck loads

(OP)
Thanks, that's exactly the sort of answer I was looking for!

RE: Car park deck loads

why not ask the architect to ask his structural guy to give you prelim loads?

RE: Car park deck loads

(OP)
Have tried and tried and tried...us Geotechnical engineers are bottom of the food chain, the STR guys don't think it's worth their time and effort to tell us things like loads, levels, settlement tolerances and all the other useful stuff that makes our reports a whole lot more relevant to their project and give much better value.  Lucky to get a proposed layout dwg half the time!   

RE: Car park deck loads

well, if thats the case, state your assumptions, and bitch to your client. unless your working for the structural engineer, a owner usually can make stuff happen when he waves the project in front of someone.  

RE: Car park deck loads

That is an irresponsible attitude on the part of the structural engineer.  Your question about anticipated loading is entirely appropriate and standard practice.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources