×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Lock-Block Retaining Walls

Lock-Block Retaining Walls

Lock-Block Retaining Walls

(OP)
During an excavation for foundations, lock blocks were placed to support the neighboring excavated profile. The total height of lock blocks is about 3.5 m. (5 rows).  The blocks were positioned on top of each other with no reinforcement by a contractor. The gap between the lock block and the sloping ground has not been back filled except partially.

I am looking for a methodology to reinforce the existing lock-blocks to provide additional lateral support for the blocks without being have to remove the lock blocks. Thank you.

RE: Lock-Block Retaining Walls

I'm not exactly sure what the lock block system is but I'm assuming they are large segmental precast blocks. You could use geogrid. To avoid taking down courses to install the grid. You could drill some threaded rod into the back of the blocks say 4-6' on center and run steel pipe (6" dia maybe) continuously across the back of the units. Then wrap geogrid around the pipe and extend it back however far you need to to resist external and internal forces. Also you may want to check the pipe for bending and the threaded rod for pullout.
 

EIT

RE: Lock-Block Retaining Walls

Also I found the manufactures to be very helpful so you may also want to contact LockBlock. They may have some suggestions.

EIT

RE: Lock-Block Retaining Walls

This is a possible place for drilled-in tie-backs, grouted rods.  However, the rigs that do that usually are heavy and they usually stand on the base of an excavation.  That means probably filling against the outside of that wall for that support on a temporary basis.

Apparently the "wall" is not holding back much other than lower backfilled area.  Seems like a cheaper way would be to remove blocks down as far as possible and then install soil nails by hand held drills.  Not the best  alternative, short of cantlevered sheet piles.

If there is some serious risk of losing the adjacent land, I'd fill the hole and start over doing it right.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources