INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Anchor rods cast-in without enough projection

Anchor rods cast-in without enough projection

Anchor rods cast-in without enough projection

(OP)
Hi all,

A few of the anchor rods for a single storey building (steel frame with x-bracing) were cast-in with barely enough projection where only a few threads are intercepted by the nuts. Other rods had just enough projection for the whole nut (top of rod flush with top of nut.)

Some of the bases can see some tension (100kN - which is not extremely high) at the cross-bracing joints. I was thinking perhaps just plug welding the nuts to the rods, does anyone see an issue with this? Should I have the contractor plug weld and in addition use new epoxy anchors?

I remember reading a while ago a rule of thumb that states rods/bolts should project 1.5" beyond the nut. I am wondering what structural reason there is for that and why wouldn't a nut that is flush be sufficient? (obviously a rod/bolt with just a few threads into the nut is not sufficient)

Thank you in advance,  

Clansman

If a builder has built a house for a man and has not made his work sound, and the house which he has built has fallen down and so caused the death of the householder, that builder shall be put to death." Code of Hammurabi, c.2040 B.C.

RE: Anchor rods cast-in without enough projection

Design Guide 1 has some fixes for this situation.

Coupling nuts are one option. This will require oversizing the holes in the baseplate and then using custom plate washers.

Welding the nut is not recommended

You can also weld extensions to the anchors if the material is weldable.  

RE: Anchor rods cast-in without enough projection

Toad pretty much nailed it... also, if the nut is flush with the threaded part, that should be adequate... threads outside the nut are about as useful as 'runway behind you'...

Dik

RE: Anchor rods cast-in without enough projection

You might drill and epoxy new anchors.  See Hilti for ideas

RE: Anchor rods cast-in without enough projection

x2 on the Elecone - assuming that the base plate hasn't been grouted yet & depending on your anchor diameter (I don't think they're available below 3/4"). They're simple to install and easy to check that it's been done correctly.
 

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources