INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Jobs

Using higher concrete mix than specified as per design.

Using higher concrete mix than specified as per design.

(OP)
What is the consequence of using higher concrete mix design than specified as per design.

Say 50MPa of concrete mix was used instead of 40MPa on bridge overpass crosshead. Engineer's intention is to removed the forms at an earlier days as specified.

I am working in Melbourne, Australia where the specs that we are using are based on VicRoads Specs. Please refer to attached file

Can you please provide comments and assessments whether the scenario is acceptable considering catching up on forecast program schedules. Thanks.  

RE: Using higher concrete mix than specified as per design.

Although not strictly in compliance with the 7 day clause for removal, I believe a good case has been made in this instance.  If this were an element where early age deflection under self weight was a problem, my answer would be different, but bridge crossheads are typically very stiff, so I would lean toward allowing the early removal.  

RE: Using higher concrete mix than specified as per design.

(OP)
Thanks hokie66 for the comments.

One of our engineer's concern is that the increased cement content in the 50MPa mix will increase the risk of early thermal cracking in the massive pier due to higher heat of hydration during concrete setting and also due to higher shrinkage which will occur in the long term.

Cheers.

RE: Using higher concrete mix than specified as per design.

We use a lot of 50Mpa concrete in buildings without much thought to those issues.  In bridges, I don't know.  The extra cement is a minor component of what causes shrinkage cracking.

RE: Using higher concrete mix than specified as per design.

That amount of excess is probably not much of an issue.  If heat is an issue (for DEF formation), then that's a whole other issue that would need to be addressed by monitoring temps. If the least dimension is greater than 1.3 meters, mass concrete concerns should be examined.
Shrinkage will be an issue is the mix design does not consider it, but this is not purely a function is 28 day strength.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources


Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close