×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Adding to existing undersize fillet weld

Adding to existing undersize fillet weld

Adding to existing undersize fillet weld

(OP)
Have a situation where existing welds that connect standard shear connection clip angles to beam webs are undersized.  The connections are of filler beams to spandrel beams.  Need to get a 1/4" leg size on the weld, and at present have only 1/8 to 3/16".

The simplest thing to do seems to be to get the primer and slag off the as-built welds, and then give them another pass.  However, the this seems like it may take more skill than is available. The structure is up, and the work will be difficult and partly overhead. I am concerned that getting a thicker leg size may not be possible.  

The clip angles are 5/16" thick, beam web is 3/8" thick.

Anyone ever had this problem?  Any suggestions?  Thanks for
any comments.

RE: Adding to existing undersize fillet weld

I would recommend adding to the weld if there is not other additional connection approach (such as adding a seat to the beam).

No preheat is required unless the steel is Grade 55 ksi or above.  Your legs and thicknesses are small enough to avoid that.

I would make sure that during the welding, the beam will not loose its support due to temporary melted weld material...perhaps a temporary screw jack column under the beam would be a good idea.

RE: Adding to existing undersize fillet weld

You could consider drilling and bolting connection.

RE: Adding to existing undersize fillet weld

Often the specified sizes of welds has less to do with the structural requirement and more to do with code requirements or what looks/feels right to the designer or has a large factor of safety.

Repairing an installed structure can be expensive, but worse than that it is more difficult to maintain the same quality standards as in the shop. You could potentially solve one problem and make others.


If you have not done so already I would do some calculations to determine if the current weld size is or is not fit for purpose. If the main failure criterion is fatigue the bigger welds may not increase the life of the structure indeed the lower standard of welding may make its life shorter.


TERRY

RE: Adding to existing undersize fillet weld

JAE,
Please explain about steel Grade 55 ksi. Is this minimum tensile or yield strength?

RE: Adding to existing undersize fillet weld

Check out AWS D1.1 - Chapter 4 "Technique" includes a table (Table 4-3) that specifies required preheat for various steel grades and thicknesses.

Preheat's main purpose is to control cracking due to high cooling rates of steel.  Thus, a thicker plate has a larger "heat sink" that can draw heat away from a fresh weld and initiate cracks.  Also, for the chemistry of the steel, the higher the carbon content (as well as the presence of other elements) the lower the critical cooling rate and the greater necessity for preheating.   Higher grade steels tend to loose ductility more with cooling.

The Lincoln Elec. Co. offers the following in their Procedure Handbook:

Hardenability can be expressed in terms of a "carbon equivalent" (Ceq) Various formulae have been developed (empirical) that give this number once you know the recipe for the steel:

Ceq = %carbon + (%Mn/6) + (%Ni/15) + (%Mo/4) + (%Cr/4) + %Cu/13)

(valid only if alloy contents are less than the following:
0.50%C
1.60% Mn
3.50% Ni
0.60% Mo
1.00% Cr
1.00% Cu

Approximate preheat temperatures:

Ceq up to 0.45% - ....preheat is optional
Ceq 0.45 to 0.60% ....200 to 400 deg F
Ceq over 0.60%    ....400 to 700 deg F

AWS table 4-3 would probably be the governing "code" rule, however.

RE: Adding to existing undersize fillet weld

SamDamon---Sorry to come in late on this question.  This is probably THE most common problem in structural steel erection.  Most often we catch it BEFORE it goes up but, sometimes it gets by the inspector.  Unless it is something totally unique in design and, I sense from your post it is not, then just have a qualified welder (I would prefer a Certified Union Ironworker) clean up the existing weld and run another pass.  If the field beam is loaded, put a jack or some type of temporary support under the end that is being worked on.  NOT rocket science if you use a little common sense.  Good luck and keep your inspector in the 'loop' to avoid future problems.

Rod

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources