INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Measuring thickness at crevice area -what is the best NDT method?

Measuring thickness at crevice area -what is the best NDT method?

Measuring thickness at crevice area -what is the best NDT method?

(OP)
Dear team members,

Good morning to all, During our on-stream inspection at jetty facilities area, we noticed most of the area in between pipe to pipe support were corroded(crevice corrosion) with sign of metal loss. Some of these piping especially small bore had been lifted, descaled by using hand tool and measured the actual thickness by using pit gauge. But the problem is, how about the big bore piping. Is it any NDT method that we can employ to measure the actual thickness of corroded area without lifting the particular piping. Appreciate if team members can also give the best preventive action. Looking forward for the response. Thank you Regards

RE: Measuring thickness at crevice area -what is the best NDT method?

Cracker,

If it's critical you measure the corrosion at these inaccessible spots and an internal inspection cannot be performed, I recommend you consider the following approach for each location where an examination is required:

1. Install a temporary support near original support location.

2. Cut or unbolt and remove existing support.

3. Clean and inspect pipe using pit gauge or UT (ultrasonic).

4. Repair and recoat (or replace) pitted sections.

5. Reinstall existing support (or install new support) using insulation material to prevent pipe-to-support contact.  Consider installing a wear pad if appropriate.

6. Remove temporary support.

If internal inspection is available, try using a UT tool (inspection pig).  Modifications may be required to the pipe to run the tool through the line.  

Hope this helps.

Jerry Myers, P.E. (Chemical/Mechanical)
Senior Engineer

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources