INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Concrete pull out check
2

Concrete pull out check

Concrete pull out check

(OP)
Very silly question but I haven't done a concrete pull out check for a set of anchor bolts (in a pier) in a long time. What ACI section should I be using?

RE: Concrete pull out check

Appendix D, and welcome to the nightmare. I'd skip it and develop your anchor rods via a splice or some other means of anchorage unless you have very low uplift.

RE: Concrete pull out check

Appendix D.
Good luck with that.

RE: Concrete pull out check

I through-bolt whenever I can to avoid Appendix D entirely.

RE: Concrete pull out check

Appendix D and then a sanity check!!
However, HILTI and some other anchor bolt companies have free downloadable programs that will jump eagerly thru all the hoops req'd.
The computer never complains.

RE: Concrete pull out check

Wow it's not that bad.

ACI-318-05/08 App. D is the section you are looking for, 08 has better pictures and explanations.
 

RE: Concrete pull out check

(OP)
@a2mfk, when you say develop the AB via a splice, is there a special type of anchor rod I would need for that? I am having a difficult time picturing this.

RE: Concrete pull out check

He is referring to ACI 318-08 Section D.4.2.1, which allows you to design reinforcement to restrain concrete breakout, Section D.5.2.9 describes the design of the reinforcement along with how far the reinforcement can be from the anchor bolts.

Here are two article for some guidance

http://www.structuremag.org/OldArchives/2004/july/From%20Experience.pdf

http://www.bechtel.com/assets/files/TechPapers/design-of-anchor-reinforcement.pdf
 

RE: Concrete pull out check

(OP)
Sandman, thank you.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources