Gas Turbine storage
Gas Turbine storage
(OP)
Hi,
My project will receive three 400 MW gas turbines which are new but have been stored at the OEM for about 1 year since their manufacture. My question is: what best practices should have been employed for storage of these units and what tests/inspections should be performed at the OEM works prior to shipping the units to the construction site?
Thanks in advance for your advice.
My project will receive three 400 MW gas turbines which are new but have been stored at the OEM for about 1 year since their manufacture. My question is: what best practices should have been employed for storage of these units and what tests/inspections should be performed at the OEM works prior to shipping the units to the construction site?
Thanks in advance for your advice.





RE: Gas Turbine storage
RE: Gas Turbine storage
full borescope inspection
visual inspection of bearings.
RE: Gas Turbine storage
RE: Gas Turbine storage
These specs are usually given to customers that will have the unit sitting waiting to be installed... the reason being that the warranty is limited if the units were not taken care of properly prior to installation.
One option is to have them produce those specs and the records showing that they complied with their own specs.
saludos.
a.
RE: Gas Turbine storage
RE: Gas Turbine storage
Regards,
Guru