INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

well inspection

well inspection

well inspection

(OP)
about how long (how many days) should it take to pull the pump out of a 200 - 300 foot deep, 6" diameter well, bail, brush and acid clean the screen, and video inspect the well?

RE: well inspection

I can comment on the pump pulling and video logging:  If the well is a typical submersible well and nothing goes wrong, both should be able to be done in one day including reinstalling the pump.  However, things can go wrong.  I was recently inspecting a pump replacement on a 8" well with submersible pump set around 400 ft.  The pitless adapter would not budge.  It was either set off-kilter or rusted in place.  It was something the well contractor couldn't help.  At one point his rig hydraulics gave way because he tried pulling too hard.  Anyway, what should have taken one day took three after having to excavate down to the pitless adapter and arrange for a welder to come out and cut it out.  Once it was removed it took a day to pull the pump and replace it.

I've seen several video loggings done for wells deeper than 400 ft and it should take 2 - 4 hours depending on set up time.

You may want to read over the acid cleaning spec to see if the acid has to be left in contact for any period of time.

You could always call a few other well contractors and tell them you're putting together a cost estimate for this and need a time estimate to propose a budget.

RE: well inspection

It will take about a day to remove the pump. I would expect that it would take a total of 3 to 5 days to remove the pump, acid treat, and video the well.

It will take another 3-5 days to reinstall the well pump and disinfect. The flushing, disinfection and sampling takes a minimum of 3 days.

RE: well inspection

(OP)
ok, bimr has confirmed our estimate. thanks

RE: well inspection

With the Acid, add at least a full day to flush the acid out.
Some acids result in positive coliform samples, which add 1-2 days per sample.  I have seen a 4 day delay in restarting the well due to positive coliform samples when acid was used.

Hydrae

RE: well inspection

(OP)
thanks hydrae
these are dewatering wells, not potable. how does that affect the disinfection requirement?

RE: well inspection

Since you are not using them for potable supply, then you only need to follow your state water resources requirements on disinfection and aquifer contamination if there is any.
 
Most of us who follow this forum, use wells for drinking water supply. Your question on how long it should take made us assume you were looking at how long you need to provide alternative supply whether storage or other sources.

Hydrae

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources