Uplift Connection Procedure
Uplift Connection Procedure
(OP)
hello all, im looking for a detailed procedure for the uplift connection detail for a timber pile, design and construction procedure would be very helpful. thanks
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS Come Join Us!Are you an
Engineering professional? Join Eng-Tips Forums!
*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail. Posting GuidelinesJobs |
Uplift Connection Procedure
|
RE: Uplift Connection Procedure
Regards,
![[pipe] pipe](https://www.tipmaster.com/images/pipe.gif)
Qshake
Eng-Tips Forums:Real Solutions for Real Problems Really Quick.
RE: Uplift Connection Procedure
RE: Uplift Connection Procedure
RE: Uplift Connection Procedure
RE: Uplift Connection Procedure
The bolt location and number is similar to the above. Determine the minimum edge distances for what bolts you want to use and then determine if the bolts will shear off or crush the wood. The smaller of the two governs and with that you can determine how many bolts to use and then find the total resistance of that part of the connection.
Next compare the rebar total to the bolt/collar total and see which will govern. Alternately it's likely the rebar will be high so you can set your total bolt force to that and determine how many bolts to use.
Regards,
![[pipe] pipe](https://www.tipmaster.com/images/pipe.gif)