INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

fused cutout before sectionalizer 35kV

fused cutout before sectionalizer 35kV

fused cutout before sectionalizer 35kV

(OP)
Is there a code or standard that would prevent me from installing a fused cutout on a pole before a sectionalizer switch pole.  Or should I install the switch before the fuse?

I am at 35kV in the USA and the scetionalizer switch will be a scada mate 5801 and the fuses will be before it.  The switch before the fused cutout is owned by the utility.   

RE: fused cutout before sectionalizer 35kV

You normally put a recloser or switch ahead of (closer to the source) any fuse cutouts.  Fuses will operate for any short circuits on their load side.

A scadamate can be monitored and controlled remotely.  If the fuses were ahead of the switch, you've lost the ability to sectionalize up to the switch.

There's no standard covering this.  It's just considered good practice.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources