INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Revamp an old chiller

Revamp an old chiller

Revamp an old chiller

(OP)
I have a 150 Tr Chiller made by Dunham-Bush. Condenser and evaporator are in the end of life and I need to replace both very soon. I don't have detailed dwgs for both and it looks like what has remained from the manufacturer is not able to locate any detailed drawing.
I am looking for a Golf based engineering office that can perform a reverse engineering and provide detailed drawings for both vessels.  

RE: Revamp an old chiller

I would suggest that the repair cost (reverse engineering exercise, the construction of the new vessels and the lifetime maintenance of endless purging and refilling refrigerant *when* it leaks) will exceed that of a nice, new, more efficient, under-warranty chiller.

Also, if the evap and cond are poked, why would you think the old compressor is worth the exercise?

 

RE: Revamp an old chiller

(OP)
KiwiMace,

Thanks for your reply. We are actually evaluating 3 other alternatives as well. A completely new unit with the same Tr. Another new unit, but bigger to replace two existing units and a redesign in our process to optimize the refrigeration demand.

 

RE: Revamp an old chiller

150TR chillers are cheap. You can even go modular and get N+1 redundancy for a reasonable capital outlay. I have done a lot of rebuild vs. replace feasibility studies and have yet to have a rebuild bear out the total operating cost vs. a new plant in even a short 5 year LCC.

In appropriate tonnage ranges the magnetic bearing units slay the old stuff. I have a plant retrofit under construction right now with one that has a projected simple payback over rebuild of less than 3 years, and that's holding energy costs stagnant. An NLPV of just over 0.3 kw/ton can do that.

Not to mention the fact that, if you extend chiller life for another 5-7 years, will you still be able to get refrigerant for it WHEN it leaks(and it will leak)?

www.ellisconsultingengineers.com

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources