INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Building expansion joints

Building expansion joints

Building expansion joints

(OP)
Hi I am looking for some general advice on expansion joints in steel frame buildings using precast or composite flooring. What are typical distances etc people use

RE: Building expansion joints

40 m in Spain for both concrete and steel structures from 1960's to 2005; comment added that reduced to 30 m if the columns' stiffness was big, and augmented to 50 m if weak. These distances were given as those to which temperature effects could normally be dismissed, yet it prescribed ranges of temperatures for which needed to be checked, that were all except those buildings where insulation etc ensured the structure lived within +- 10ºC range. Generously interpreted that could mean well insulated buildings but everyone sees that not if considering the temperature at which built.

Current national code CTE as it stands would be more or less the same (40 m exemption of need to include temperature effects in the analysis for the ordinary buildings) except that has a more complicated prescription for temperature loads (must be akin to eurocode, many new things in it are); so as of now, in the end, the strict view is that you are to include the temperature effects and see that the serviceability limits are respected, whatever the length between joints; if only because they may be adding to other deformations and then not meeting targets of sound behaviour. This becomes truly required if 40 m are not respected.

Note that in general the distance between structural (building) joints are just a device related to the obliged consideration or not of temperature effects in the analysis. So you can project a building of any size as long as you prove its wanted sound behaviour is respected. Think for example of long span bridges; temperature has then its own relevance.

I have seen thermal cracks on façades 15 m long and inner (thermal) cracks on 12 m long. I have also seen cracks in irregular buildings 51 m long. Yet other where the outer skin is jointed (prefab could be, perhaps more typically curtain-wall and inner masonry is mostly floating on the structure have no problems at far bigger dimensions, say, 80 m long.

CTE when speaking of supported -not load bearing- masonry also specifies shorter lengths of continuous masonry work as per the attached table. Vertically I think there are other restrictions.

RE: Building expansion joints

The Modern Steel article posted by SteelPE is a really good primer with formulas as well...

RE: Building expansion joints

(OP)
Thanks guys. Links very useful, I am uk based but still applicable.  

RE: Building expansion joints

Yeah, I saw where you were from, but the forumulas are pretty simple with a little Imperial-SI translation the structure wouldn't know the difference!

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources