INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Planned vs. Actual

Planned vs. Actual

Planned vs. Actual

(OP)
Hi,

  I'm trying to use MS Project 2007 & made a WBS, which demonstrates the 'planned' schedule fairly well.  Now, how do I demonstrate or show the actual & compare the two through the Ghantt chart?

Thanks
 

RE: Planned vs. Actual

Once your original planned program is agreed with all stakeholders, you then need to set the baseline. This holds your original as it is now.

Once done, you monitor your program (daily/weekly or what ever duration suits), and you enter your actual start, and when complete your actual finish dates.

I tend to enter these on the screen as per attached. You split your screen, click on more views (far left hand toolbar, bottom icon).

RE: Planned vs. Actual

(OP)
Hi Iken,

  Thanks for the info.  How do you manage or show scope changes?

RE: Planned vs. Actual

If the scope changes increase the program duration you can then ammend your program (add new tasks/durations) and then save another baseline (name it rev1 for example).

I am in the construction area at the moment, and while you can argue most variations etc do impact on the program, reality is unless there is an extensive impact on the program - the end date never changes.

RE: Planned vs. Actual

(OP)
Hi Iken,

  So, it appears that I need to have multiple baselines to be able to view planned vs. actual.  Now, I need to go figure out on how to create multiple baselines.

Thanks
 

RE: Planned vs. Actual

You set the baseline under Tools/Tracking/Set Baseline.

There is a pull down menu giving a number of baselines (1 to 10 +...)

I would only set a new baseline if you are intending to go for (or already have agreed) and extension of time. If the additional scope of works do not push pout your end date, to not bother. You could instead just have a side (mini) program for these additional works - if they do not impact the final end date.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources