Planned vs. Actual
Planned vs. Actual
(OP)
Hi,
I'm trying to use MS Project 2007 & made a WBS, which demonstrates the 'planned' schedule fairly well. Now, how do I demonstrate or show the actual & compare the two through the Ghantt chart?
Thanks
I'm trying to use MS Project 2007 & made a WBS, which demonstrates the 'planned' schedule fairly well. Now, how do I demonstrate or show the actual & compare the two through the Ghantt chart?
Thanks





RE: Planned vs. Actual
Once done, you monitor your program (daily/weekly or what ever duration suits), and you enter your actual start, and when complete your actual finish dates.
I tend to enter these on the screen as per attached. You split your screen, click on more views (far left hand toolbar, bottom icon).
RE: Planned vs. Actual
Thanks for the info. How do you manage or show scope changes?
RE: Planned vs. Actual
I am in the construction area at the moment, and while you can argue most variations etc do impact on the program, reality is unless there is an extensive impact on the program - the end date never changes.
RE: Planned vs. Actual
So, it appears that I need to have multiple baselines to be able to view planned vs. actual. Now, I need to go figure out on how to create multiple baselines.
Thanks
RE: Planned vs. Actual
TTFN
FAQ731-376: Eng-Tips.com Forum Policies
Chinese prisoner wins Nobel Peace Prize
RE: Planned vs. Actual
There is a pull down menu giving a number of baselines (1 to 10 +...)
I would only set a new baseline if you are intending to go for (or already have agreed) and extension of time. If the additional scope of works do not push pout your end date, to not bother. You could instead just have a side (mini) program for these additional works - if they do not impact the final end date.