Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Fence Foundation Embedment

Fence Foundation Embedment

Fence Foundation Embedment

(OP)
I have an 8' tall security fence that is attached to a 4' deep x 1.5' wide continuous concrete pedestal/footing. There is a 2' separation grade between the two sides of the pedestal and the pedestal is embedded 2' on the shallow side. I am trying to determine if the 2' embedment is adequate for wind loading.

I know that there are formulas in IBC for embedment depths of circular posts, but my application is for a continuous footing. Thus, I'm not sure that I can use those formulas.

I also tried looking at the pedestal as a sort of "gravity retaining wall" with a wind load, but the embedment depth required comes out to 4+ feet. This doesn't make much sense compared to a Standard Plan of a Noise Wall that I have which only requires 3'-3" embedment for a similar wall height...and the noise wall is a solid wall whereas my fence is not.

Have any of you had any experience doing something like this? If so, what Code or approach did you use to check for embedment?

Thanks for the help!

RE: Fence Foundation Embedment

If you have cohesive soils, you may try a trench footing.  Not too long ago, we used to support a 3 story townhouse on 8 inch wide and 48 inch deep trench footing.  If you have sandy soils, you may try a grade beam.  Foundation design books like Bowles or Peck and Hanson will have the necessary equations.

RE: Fence Foundation Embedment

Here's a thought: Take a 2" tall temporary jersey barrier with a fence on it, does anyone ever think about it overturning?

Why not assume a similar condition, that it's free standing? Apply a wind load to the fence, then sum the moments about the base of the foundation. My gut feeling is that it's not going anywhere under normal circumstances.

RE: Fence Foundation Embedment

Agree with BB...It usually only takes 10 to 12 inches of embedment to achieve fixity, but you have two considerations to make....the embedment for fixity and the contact stress on the concrete due to the moment at the foundation interface.

One of my clients uses embedded columns for their canopy products.  It usually only takes 12 to 14 inches of embedment, but have to check bond for pullout and check contact stress for grout fill and concrete.

RE: Fence Foundation Embedment

Have a couple of beers and it won't be a problem anymore.  

I agree with BB and Ron.  

Mike McCann
MMC Engineering
Motto:  KISS
Motivation:  Don't ask

RE: Fence Foundation Embedment

Too bad we can't solve all of life's problem with beer. sad

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources