INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Seismic Bracing Electric Duct Trapezes

Seismic Bracing Electric Duct Trapezes

Seismic Bracing Electric Duct Trapezes

(OP)
I am trying to design seismic bracing for electrical duct trapeze supports. I have long hanging distances but mainly I have multiple levels of of trapezes. Also, the installer is hanging additional trapezes from various points along the supporting strut. There really is no rhyme or reason to their support. (See Sketch)

I want to isolate only the ducts requiring seismic restraint. I thought about adding a piece of strut above the ducts that require bracing, strap the ducts to the bottom of the new strut, and remove the existing straps holding these ducts to the existing strut below the ducts. The new rod and braces will be designed only for seismic loads. The existing will only be there for dead loads. (see sketch) Any thoughts?

Do I have to add rod stiffeners to the existing threaded rod just there for dead load or just to the new rod there for seismic bracing? Will the existing rods go into compression or do I not consider them?

Thanks!

Clarke Engineering Services, PC
Jobsite Engineering and Consulting
www.anchorengineer.com

RE: Seismic Bracing Electric Duct Trapezes

If there are unimportant tiers supported by the same verticals, they will be excited by the earthquake just as much as the important ones. If the downcomers are rods,The vertical kick from the diagonal could be trouble if the aggregated horizontal force is high enough.

I don't want to go further, we did dynamic analysis for cable tray supports on the nukes. There is a danger that I might go overboard here.  

Michael.
Timing has a lot to do with the outcome of a rain dance.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources