INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Culvert Extensions

Culvert Extensions

Culvert Extensions

(OP)
Hi

I was wondering if there is a typical length that needs to be removed or cut off from an exisitng culvert before joining it with a new extension? If so, is it the same for CMP and CBC?

Any help will be greatly appreciated

Thanks

RE: Culvert Extensions

The only time we have the contractor remove or trim portions of an existing pipe culvert (CMP or RCP) is if the end is damaged.  After a field inspection, we determine the length of removal.  For concrete box culverts we typically do not need to remove any length unless there is damage.  If there is significant damage, then the entire structure needs to be evaluated for structural integrity.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources