×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Bracing of Piles

Bracing of Piles

Bracing of Piles

(OP)
In NYC Building Code, it requires all piles to be laterally braced.  

One of the provision states :
Single-pile or two pile groups or a single line of piles may be considered to be adequately braced if connected to, and braced by, a self supporting floor system provided : (1.) that the details and dimensions of the floor and the wall or pier are of adequate strength to resist lateral displacement of the pile cap under conditions of maximum eccentricity of the applied load; (2) that the wall or pier is braced until connection of the floor framing is made and the flooring (or slab) is in place.

Can someone help me to interprete the above?  What is a self supporting floor system?  If I have a pile supported structural slab, what am I supposed to check/calculate to make sure that all my single pile and two pile groups are adequately braced?

Also, I have a retaining wall which is to be pile supported too.  What should I do to ensure that it is laterally braced?

Thanks for your help.

RE: Bracing of Piles

I don't know about the slab but retaining walls are usually constructed at or below grade to retain fill.  As such the pile are usually entirely below grade and bracing is not only unecessary it is impractical.

As for the floor slab, the same would be true if the slab were placed on grade yet supported on pile.  Something that's been referred to as a "Land Pier".  

It appears that the code is addressing stability both globally and local.  However if your pile are not unbraced for some height above ground, then the soil will act to brace each pile.

RE: Bracing of Piles

I agree with Qshake, but your Geotechnical engineer should review the soil for potential liquefaction. Under some seimic conditions the jello we call soil could lose some stiffness. This could pose a problem, requiring grade beams or the like to connect the pile caps.

RE: Bracing of Piles

Regarding liquefaction, concerns for this type of soil failure really need to extend beyond the structure.  Soil remediation (dynamic compaction, stone columns etc) would be an effective and likely solution but not bracing pile.  Remember the photos of the japanese buildings leaning over in the 1964 Niigata earthquake; If those buildings were founded on piling, bracing would not have improved the performance of the building.  In fact the buildings were relatively undamaged although they were unusable.

Qshake.

RE: Bracing of Piles

The bracing of the pile caps is done using tie beams if not braced by a floor diaphragm.  Most seismic codes require tie beams.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources