INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Lightweight fill to raise composite floor elevation

Lightweight fill to raise composite floor elevation

Lightweight fill to raise composite floor elevation

(OP)
We have a floor space that will be designed for a 4" raised access floor on a composite beam floor system.  

The Owner would like the option to eliminate the raised access floor after construction and add some sort of 4" concrete topping.

I'm thinking of lightweight concrete bonded to my concrete slab on metal deck, but wondered if there are other options out there.  

Thanks!

RE: Lightweight fill to raise composite floor elevation

Some kind of lost formwork forming vaults

http://www.caviti.es/
 

RE: Lightweight fill to raise composite floor elevation

Not 100% clear on this question?  

When you say 'after construction' does that mean 10 years from now, or still during construction phase?   How much floor area are we talking about (just a room, an entire floor, etc)?

4" bonded topping would work - will this floor be exposed?  If so, pay attention to crack control, etc. in the new topping slab.  I would use Fibers in mix and cut crack control joints on girder lines.  

In floor structure design, be sure to account for the additional 4" thick concrete load (superimposed, POST composite load).  I would assume normalweight concrete.......when they get a contractor in there to do the work 5 years from now, unless specifically told, they are just going to place the cheapest product (normalweight concrete).  Lightweight is harder to pump too.

Unless I am missing something, I don't see how the 'forming vaults' relates to this question?  Looks like a cool product though.

RE: Lightweight fill to raise composite floor elevation

Well, I have thought the question asked was most constructive than structural, means available to raise somewhat some level; here it is used normally at ground levels to form a cavity on a lost base of concrete, and even over mats to permit water flow to drains to pumps where it is thoght sometime such incidence might happen. I think from the question the structural aspects do not escape to whom is asking and so I interpreted the question this way.

RE: Lightweight fill to raise composite floor elevation

(OP)
Thanks for the replies.

"After Construction" means 1 month to 1 year after the slab is placed.

The topping would be applied to the entire floor, which would be roughly 90ft x 200ft.

Right now, I am thinking 4" lightweight concrete with wire mesh.

Some ideas that have been thrown around include styrofoam w/ concrete topping, but i dont have a comfort level with that.

RE: Lightweight fill to raise composite floor elevation

Plan for the weight of 4" of lightweight concrete, then if they decide to go another route, you're covered.  I would only consider the extra concrete to be dead load, I wouldn't consider it to be adding strength as part of the composite floor system.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources