Concrete Foundation - Earthwork takeoff
Concrete Foundation - Earthwork takeoff
(OP)
We have a 3 story building with a partial concrete footing and partial slab on grab. Is there normally a rock section underneath this slab and footing. Trying to do an earthwork takeoff for the excavation





RE: Concrete Foundation - Earthwork takeoff
Differing site conditions may require different
support/drainage courses under slabs/footings.
If you have access to the geotechnical report,
check for recommendations there also.