Verifying load capacity of H-piles driven by vibratory Hammer
Verifying load capacity of H-piles driven by vibratory Hammer
(OP)
I am looking at driving H-piles at a site that has a deep (~150') layer of loose silts before hitting hard pan clay.
I would like to use a pile driving analyzer to verify pile capacity, or at least get blow counts for the end bearing material, but my customer is leary of bringing any impact hammer on site at all due to cranky neighbors. He wants only vibratory hammers used.
Any advice?
I would like to use a pile driving analyzer to verify pile capacity, or at least get blow counts for the end bearing material, but my customer is leary of bringing any impact hammer on site at all due to cranky neighbors. He wants only vibratory hammers used.
Any advice?





RE: Verifying load capacity of H-piles driven by vibratory Hammer
RE: Verifying load capacity of H-piles driven by vibratory Hammer
www.PeirceEngineering.com
RE: Verifying load capacity of H-piles driven by vibratory Hammer