Why both restraints and thrust blocks?
Why both restraints and thrust blocks?
(OP)
Why is it that some municipalities demand both joint restraint and thrust blocking? I guess thrust blocks can be altered or removed during subsequent work on other utilities. So backing up thrust blocks with restraints could make sense. But why should restrained joints be backed up by thrust blocks? Do they think the restraints may be removed or damaged? Or that they may corrode? Maybe they wish to guard against poor workmanship or design...
Thanks
Thanks





RE: Why both restraints and thrust blocks?
From my experience it is a lack of knowledge in why restraining the fitting, with either thrust blocks or mechanical restraints, is necessary. They feel that if one of them is good by itself, it must be even better if you use both. A big waste of money if you ask me.
RE: Why both restraints and thrust blocks?
RE: Why both restraints and thrust blocks?
Of course large concrete reaction blocks and walls are also used by some designers in locations on welded or fused steel and plastic pipelines, not necessarily out of fear that the welded or fused joints cannot handle the pressure thrust loads imposed, but instead most generally to strictly control deformations or movement, or in the cases where some of the multiple drivers for same are cyclical (e.g. temperature), rebating deformations or movements.
If you are running into folks wanting both for a particular thrust application, it might not hurt to ask them why. While I agree with some said, some such battles may not be worth fighting.
RE: Why both restraints and thrust blocks?
RE: Why both restraints and thrust blocks?
When are pipe restraints harmful? I deal with pipe restraints for <16" diameter water and sewer lines, and the design process is straightforward. Restraints are cheaper, quicker, and easier to install than thrust blocks. What is the downside?
RE: Why both restraints and thrust blocks?
Wherever you don't need one. Every time you put one in, deflection and strain is reduced, but stress increases.
RE: Why both restraints and thrust blocks?
RE: Why both restraints and thrust blocks?
RE: Why both restraints and thrust blocks?
RE: Why both restraints and thrust blocks?
Seriously, I continue to argue with civil engineers who just dont get the fact that a fully welded pipe or restrained pipe does not need thrust blocks. There must be a problem in university teaching or text books, but try as I might civil engineers go on burying concrete blocks.
I point to refineries where the pipes are above ground with no thrust blocks to no avail.
"Sharing knowledge is the way to immortality"
His Holiness the Dalai Lama.
http://waterhammer.hopout.com.au/
RE: Why both restraints and thrust blocks?
RE: Why both restraints and thrust blocks?
above ground piping can be easily inspected, underground typically is buried and forgotten about and 100-year old buried lines are still in service without inspections. So providing sufficient thrust restraint is perhaps more critical.
Most water distribution systems do not operate at 180 psi. 120 psi is a more "normal" upper limit at least for the numerous systems I have been involved with over the last 25 years in the US. Since I have no experience with refineries, I can only imagine what kind of pressures are typical but would not be surprised to see them much higher than those in a municipal water system... Perhaps that is one reason for increased concern over pipe stresses.
RE: Why both restraints and thrust blocks?
If you bury them and forget them, it won't be long before they start reminding you.
RE: Why both restraints and thrust blocks?
I suggset you check out the pressure rating of class 300, 600, 900 and even 2500 flanges. All can be found in refineries. Pressures in process are far higher than in any water project.
"Sharing knowledge is the way to immortality"
His Holiness the Dalai Lama.
http://waterhammer.hopout.com.au/
RE: Why both restraints and thrust blocks?
Underground lines may have been installed for 100yearsd. Look at the statistics of water leakage! Utilities spend a fortune trying to get leakage down below 15%. This is not tolerable for petrochem.
It wouldnt happen if the pipelines were fully welded.
Sewage treatment plants are invariably designed for 6 times average dry weather flow! Why leakage. If the pipelines were fully welded PE or sement lined steel the plant size can be reduced to 1.6 times.
"Sharing knowledge is the way to immortality"
His Holiness the Dalai Lama.
http://waterhammer.hopout.com.au/
RE: Why both restraints and thrust blocks?
Regarding treatment plants, they are designed for peak flows which are generally more like twice the average dry weather flow. This is done to handle peak flows, not so much to handle I & I. Unfortunately in many parts of the world, the sewers handle both sanitary and storm water runoff. It would be interesting to see if the additional cost for piping could be offset by a corresponging reduction in treatment costs.
RE: Why both restraints and thrust blocks?
Eurpoe is way a head of the USA when it comes to using non metallic piping for sewerage systems.
Another challenge to be considered is the corrosion of the cement lining with H2S. PE/ABS/GRP/PVC resists this corrosion.
"Sharing knowledge is the way to immortality"
His Holiness the Dalai Lama.
http://waterhammer.hopout.com.au/
RE: Why both restraints and thrust blocks?
RE: Why both restraints and thrust blocks?
Sounds good....
RE: Why both restraints and thrust blocks?
RE: Why both restraints and thrust blocks?
RE: Why both restraints and thrust blocks?
RE: Why both restraints and thrust blocks?
RE: Why both restraints and thrust blocks?
The availability of good quality water made possible with USA water treatment and these systems has also very likely been no small factor in a near tripling of mean USA life expectancy since e.g. gray cast iron pipes were first introduced here in the early 1800's. It is hard to make a convincing practical case against the performance and general cost-effectiveness of even formerly supplied gray cast iron piping and even some rather ancient joining systems(that have reportedly in just North America provided continuous service to Customers, and presumably generation of revenues etc., for more than 100 years in more than 628 utilities, and in more than 23 utilities for more than 150 years). While some pipes and/or joints must indeed be replaced or renewed and leaks fixed with new technologies, in some cases it is obvious systems that were installed for a pittance a very long time ago are now still effectively delivering even better water to Customers, and still generating dollars per month revenue to the utilities.
Try as you might you will thus have a hard time convincing me that most of our forebears did not or do not now know what in the hell they were are doing at the time (or necessarily had other motives than their utility's interests, their piece of mind, and service to their tax and rate-payers)! In my mere 36 years in the industry I have been made aware of a good many other alleged "newer" ideas and types of pipe(line)s etc. that have really not made it beyond infancy.
While some welded or fused water and other pipelines, that have really come on board only for the last few decades, have shown some effectiveness in areas, they have also exhibited some unexpected problems, and it remains to be seen if they will survive as long underground(as have some other systems)with any widespread installation for water service.
RE: Why both restraints and thrust blocks?
Even a restrained joint MIGHT need a thrust block, depending on the minimum required restrained length of pipe on each side of the bend. For a buried pipeline with restraint joints (for example a welded steel pipeline), trust force is diminished by development of the friction factor between the pipeline and the embeddment soil. Certain surface (length of pipe) is needed on each pipe leg to provide enough friction force to contract with thrust force depending on:
- pipe diameter
- pipe test pressure
- angle of break
- pipe installation depth (weight over the pipe)
The formula is mentioned in AWWA M11 for water industry. If you don't have this minimum length on each side of your bend, then extra anchor should be provided by thrust block.
please note that most often this length is few meter but in certain cases (large diameter cross country pipelines with high pressure) it could reach to 200-400 meter. Then one should consider thrust block for a restrained joint pipeline.
RE: Why both restraints and thrust blocks?
RE: Why both restraints and thrust blocks?
A fully welded pipe takes the pressure by stress in the pipe wall. Do you think it would be any different if the pipe sat on a pipe rack? you dont see concrete thrust blocks up in the air and the pressure x area is certainly not transferred to the structure.
A fully welded pipe does not rely upon any soil friction to restrain the pressure.
You only need thrust blocks when the pipe is not restrained as in rubber ring jointed systems or unrestrained bellows.
"Sharing knowledge is the way to immortality"
His Holiness the Dalai Lama.
http://waterhammer.hopout.com.au/
RE: Why both restraints and thrust blocks?
I do agree with you that a fully welded pipe takes the pressure by stress in the pipe wall. That's exactly the reason that unless the pipeline is properly restrained to resist the unbalance forces, either separation can occur at the pipeline joints or pipe wall stresses could approach yield strengths. In large diameter pipelines with hight bend angles or pressure (test pressure better to say), one should control that pipe stress does not get close to the yield strength. If it gets close then extra resistance to movement should be used by increasing the bearing area (a thrust block).
A fully welded pipe (restrained joints) may resist the trust force by relying on soil friction to restrain the pressure. In fact, the trust force is resisted through the development of friction between the pipe and the soil surrounding it. According to AWWA M11, the thrust force resisted by restrained or harnessed joints is the force acting along the longitudinal axis of the pipe. So if the restrained joint is used a sufficient length of pipe must be restrained by welding or harnessing to resist the unbalanced thrust force. Here's a force diagram as per AWWA M11:
Normally, in cross country pipelines; there are few hundered meter distance between bends that means enough restrained length. However, in my opinion, the correct way would be to control either the stress or the required restrained lengths for your welded pipeline (better to say for pipelines with restrained or harnessed joints) to make sure that you are on the safe side. Otherwise, thrust blocks might be required even for the welded steel pipeline. This could be the case for large diameter and high pressure pipelines.
RE: Why both restraints and thrust blocks?
The pipe wall thickness is selcted to contain the pressure. Ie the hoop stress determines the wall thickness. This PD/2t. The longitudinal stress occurring inthe pipe wall is half of this value PD/4t.
Ergo, if the pipe can withstand the pressure there will never be a need for thrust blocks as you describe.
"Sharing knowledge is the way to immortality"
His Holiness the Dalai Lama.
http://waterhammer.hopout.com.au/
RE: Why both restraints and thrust blocks?
But still I am thinking about the force (the summation of the 2 force vectors parallel to pipe shown in the previous post) that is exerted at the bend.
Consider the pipeline shown on the previous figure to be a free body. The thrust force with NE direction wants to move the bend toward NE. If the pipeline is hanged by ropes from a ceiling, then the bend moves toward NE. But since it's buried and the joints are restrained, the friction between the pipeline surface and soil develops and avoids the bend to move. More thrust force then means more required restrained length. This is what AWWA addresses in its formula.
Recently, I've read an article from ASCE, pipeline 2010 written by ASCE Task Committee on Thrust Restraint Design of Buried Pipelines. It says:
"Current restrained joint design theories for different pipe materials depend on two primary forms of resistance mechanisms to resist the unbalanced thrust forces that arise at a horizontal bend, valve, tee or other similar sources of thrust in a buried pressure pipeline. The first and most commonly recognized form of resistance is from friction and adhesion resistance at the pipe-soil interface; and the second form is from passive and/or bearing resistance of the pipe against the soil surrounding the pipe."
Unified Approach to Thrust Restraint Design, JOURNAL OF TRANSPORTATION ENGINEERING, ASCE / JANUARY 2007, states:"While providing thrust-resisting supports in an above ground pipeline can resist thrust forces, resisting thrust forces in an underground pipeline is usually accomplished with thrust blocks, restrained joint systems, or a combination of both." And:"and "As an alternative to providing thrust restraint mechanism using thrust blocks, restrained joint systems may be used. In general, the restrained joint system is a mechanical (welded or harnessed) joint providing longitudinal restraint. The objective of the thrust restraint design using a restrained joint system is to determine the length of the pipe that must be restrained on each side of the point of action of the thrust force. The primary objective of the restrained joint system design is to transmit the unbalanced forces to the surrounding soil without over stressing the pipeline wall and without subjecting the pipeline to joint separations."
Here's a figure under "Restrained Joint System Design":
Still thinking about your explanation, I would be more than happy to see comments about this discussion from you and others since I can see many "senior" names in this post.
RE: Why both restraints and thrust blocks?
I would only say in closing that while I definitely agree some modern and formidable restrained joints have indeed proven most convenient and useful, and also well proven for many years, I don't believe I would necessarily throw any tools out of the toolbox just yet, including external anchorages like thrust blocks or batter piles etc. (well-designed and constructed buttresses might prove particularly helpful if unrestrained pipes are what a Contractor or Owner has available and based on their experience and reputation trusts, and you want to get a working pressure pipeline built!) Everyone have a great weekend.
Maybe when folks get to be truly "senior", they're really only in it for the "stars"?
RE: Why both restraints and thrust blocks?
I agree with you for rubber ring jointed pipe but not for a fully welded pipe.
For a fully welded pipe the thrust is taken in the wall of the pipe and no restraint is necessary.
"Sharing knowledge is the way to immortality"
His Holiness the Dalai Lama.
http://waterhammer.hopout.com.au/