INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

API Plan 72 Support For Dry-Running Seal

API Plan 72 Support For Dry-Running Seal

API Plan 72 Support For Dry-Running Seal

(OP)
My seal vendor has provided me a copy of a proposed control panel in support of a dry-running secondary seal to use nitrogen as the "buffer" gas.

I noticed on the drawing that the order of instrumentation on the supply leg is as follows:

Filter - Pressure Regulator - Pressure Gauge - Flow Meter - Needle Valve

I have heard mixed responses on where the needle valve should be placed. Should it be upstream/downstream of the flow meter and pressure gauge. The seal vendor has advised that the needle valve should be placed after all instrumentation, but then you have no means of measuring the pressure/flow downstream of the needle valve. Am I thinking bakwards here? Thoughts?

RE: API Plan 72 Support For Dry-Running Seal

hummmm..... is this a "seal-vendor", or is he introducing their "brand new filter's catalogue"? surprise

Regards from a "seal vendor" winky smile

http://www.hidromar.es

RE: API Plan 72 Support For Dry-Running Seal

The standard drawing from John Crane for an API Plan 72 shows needle valve then flow meter.   

Johnny Pellin

RE: API Plan 72 Support For Dry-Running Seal

The needle valve should be upstream as mentioned in JJPellins response.  In the event of an operator isolating the valve it will show what is at the seal.

Hidromar How about a constructive reply to the questions?

RE: API Plan 72 Support For Dry-Running Seal

(OP)
JJ and flexibox,

Thanks for the response. That has always been my preferred approach to regulation and metering of the low pressure nitrogen purge and when my contact advised opposite it certainly surprised me.

RE: API Plan 72 Support For Dry-Running Seal

Touché, flexibox!

Sorry about to be sarcastic, I'll try to do my best for future!
 

http://www.hidromar.es

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources