INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Questions for transmission line design

Questions for transmission line design

Questions for transmission line design

(OP)
I am a civil structural engineer and interested in switching to unility engineer. Have read ASCE 10 -97 for transmission structures. am reading 1724E-200(transmission line design manual). The former is purely about structure analysis. The latter in addition to structure also includes non traditionally structure staff, like vertical/horizontal clearance, etc. all used for structure spotting. In a real work setting who will does this structure spotting, civil engineer or electrical engineer?
Is it a must for a structure engineer to command this knowledge?

Thanks  

RE: Questions for transmission line design

It was moving to CAD when I left it 20 years ago.
perhaps you should ask the mods to move this to the "Transmission Structure Engineering" board.

Michael.
Timing has a lot to do with the outcome of a rain dance.

RE: Questions for transmission line design

The civil/structural engineer will do the tower location away from the substation/generating facility, but the electrical engineer will probably get involved inside the substation - specifically the deadhead tower location within the switchyard.

 

Mike McCann
MMC Engineering
Motto:  KISS
Motivation:  Don't ask

RE: Questions for transmission line design

(OP)
Thanks to all of you.

RE: Questions for transmission line design

I have done some dead end structures in substations....the electrical guys laid the substation out

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources