INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Transferring load from old to new structure

Transferring load from old to new structure

Transferring load from old to new structure

(OP)
I'm working on a project where the existing substructure is in  poor condition, but everything from the deck beams up is ok.

We are designing/installing new piles and a new steel frame to support the deck beams so the existing substructure can be removed.

Currently for the load transfer we intend to install the new structure and then 'jack up' under the existing beams to take the load before the existing substructure is removed (alternatively we may drive in & weld wedges/packers between old & new). We'll be locally strengthening the existing beams with plates above the new supports.

Its on my list to look at later this week - I was wondering whether people had any clever methods they've used for ensuring load transfer in the past, or whether there was any particular 'bear in mind' issues people would like to flag up?

Cheers.

ukciv

RE: Transferring load from old to new structure

I prefer screw jacks as they are much more controllable than other methods.

Is there no way to remediate the substructure in place?

RE: Transferring load from old to new structure

(OP)
Sadly not, the existing piles in particular are in a bad condition.

RE: Transferring load from old to new structure

Permanent or temporary flat jacks are normally at least part of the solution to preloading the new structure.

RE: Transferring load from old to new structure

This can be complex.  What type of structure is it and how many stories?  

Are the 'new piles' being installed the 'temporary' foundations or 'permanent'?  I assume they are the 'temporary', else why are you removing the existing foundations?  

Another side note - note sure what is specifically wrong with the exsting piles - but make sure the 'Geotech' has properly spec'd the 'new' piles......is it a pile damage issue?  or soil support issue?  I assume the new piles will be installed close to the exsting ones.  And also, if the existing ones are being removed, how does this affect the new piles (voids?  effect of skin friction on adjacent piles).

My 2 cents

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources