302 HQ Stress relieving
302 HQ Stress relieving
(OP)
I am looking for help with a new product our company is working on. Does anyone know the effects of "stress relieving" 302 HQ to the following parameters. The reason I question this is because the typical stress releive would be at 1650F. I was wondering what the effects of the modified treatment would be metallurgically.
600F for 8 hrs, 16 hrs, and 36 hrs
650F for 8 hrs, 16 hrs, and 36 hrs
700F for 8 hrs, 16 hrs, and 36 hrs
Any help is greatly appreciated!
600F for 8 hrs, 16 hrs, and 36 hrs
650F for 8 hrs, 16 hrs, and 36 hrs
700F for 8 hrs, 16 hrs, and 36 hrs
Any help is greatly appreciated!





RE: 302 HQ Stress relieving
You may get a little stress relief at 700F x 16hrs but not worth the effort.
= = = = = = = = = = = = = = = = = = = =
Plymouth Tube
RE: 302 HQ Stress relieving
Thanks again
RE: 302 HQ Stress relieving
= = = = = = = = = = = = = = = = = = = =
Plymouth Tube