INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

.6D + W Question

.6D + W Question

.6D + W Question

(OP)
When calculating the vertical loads to a column for this load combination do you use the overturning wind moment to determine the vertical loads from wind (Mot/L=T=C)or do you use the tributary area x uplift force?

I have used the T=C from the horizontal Mot + wind area load + .6D but now I'm having second thoughts.  Have also noticed in some publications that the compression force from the wind Mot is neglected which does not seem correct.  Thoughts/Comments

RE: .6D + W Question

All the wind - lateral and uplift, should be applied at the same time.  Wind hitting a building will have lateral forces on the windward and leeward walls and uplift on the roof simultaneously.

You would typically use the MWFRS winds and not the C&C winds for a column in a brace system resisting wind from large tributary areas.

RE: .6D + W Question

(OP)
JAE,

Thanks for the reply and we are applying lateral and uplift  at the same time. I don't think i was clear in my original question please see below.

I have a total overturning moment calculated by the horizontal wind load x arm (height) + roof uplift load x l (distance from slab edge.  From this I calculate the T & C on the columns/pile.  This would give me the uplift per column based on the overturning.

I also calculate the uplift per column based on the tributary area.  Should I add this to the T calculated above?  If I do it seems that I would be doubling up on the wind.

RE: .6D + W Question

You use the term "overturning moment" which you indicate is from the horizontal force x height and from the uplift on the roof over the tributary area.  

This would be an analysis of the total structure using all the applied wind so the tension force you get from this overturning moment would include all the wind effects.

So if your term:
    "roof uplift load x l (distance from slab edge"

is the same as your term:
    "uplift per column based on the tributary area"

Then yes you are doubling the wind.
 

RE: .6D + W Question

You could really cut to the chase and provide a sketch showing a FBD with all of your forces labeled

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources