INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

mistake in drilling

mistake in drilling

mistake in drilling

(OP)
we had a mistake in drilling one hole in a header of a harp (hrsg boiler).
we want to build up the wrong hole by welding and again drill another hole in proximity of repaired area.
Is it permitted or prohibited according to ASME SecI or any other technical codes?
If it is permitted , is there any usual procedure for repair and test of this hole.
OD of hole is 35mm and thickness of pipe is about 34mm.
design pressure of the header is 157 bar.
pipe material is A335-P22

RE: mistake in drilling

Yes, you can plug weld the hole and re-drill. Just make aure that you document this activity as a nonconformance in accordance with your Quality system manual, and your AI is involved.

RE: mistake in drilling

You will need to produce a WPS for welding a hole. A good reference is API-6A Hole procedure.

Petrotrim Services

RE: mistake in drilling

Respectfully disagree on needing a new WPS.  Your full-penn WPS will meet the Code requirements, assuming it is not limited in joint geometry.  If it is limited, that WPS can be revised to include this welding.

Biggest issue it that you write the NonConformance Report, and get your AI involved with this repair.  Do this first, as the AI's opinion on your WPS is the only one that matters.

RE: mistake in drilling

"weld buildup"  I would use a piece, prepare it for welding,
  WPS? may or may not use same WPS ; full penetration is required with little or no reinforcing; test per your procedure and AI requirement as you may be required to UT the final weld.  but 1.1/2" or 35mm  opening is not a big sin...
Tube welding to header WPS may not be appropriate for the patch
but it could be okay,
  
 

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources